Physical AIUpdated 21 October 20268 min read

Control Panel Design in the UK: Standards and Build Checklist

A UK control panel is designed against the standard that matches its job: IEC 61439 for power switchgear and controlgear assemblies, or IEC 60204-1 for the electrical equipment of a machine, with BS 7671 governing the supply installation. As of 15 October 2026 the IET treats BS 7671:2018+A4:2026 as current and Amendment 2 as obsolete.

Control PanelsIEC 61439IEC 60204-1BS 7671UKCAElectrical Design
Electrician in a hard hat and face shield testing breakers in an open electrical panel with a multimeter

Key takeaways

  • IEC 61439 covers power switchgear and controlgear assemblies; IEC 60204-1 covers the electrical equipment of machines; they are not interchangeable.
  • The IET says BS 7671:2018+A2:2022 became obsolete for new work after 15 October 2026; use BS 7671:2018+A4:2026.
  • Electricity at Work Regulations 1989 regulation 4 requires systems to be constructed and maintained to prevent danger so far as reasonably practicable.
  • GOV.UK says Great Britain continues to recognise CE marking alongside or in place of UKCA where product regulations meet UK needs, under the 2024 amending regulations.
  • HSE notes a voltage as low as 50 V across the body can disturb the heart and breathing, so test and commission with suitable equipment and procedures.

A control panel is judged against the standard that matches what it does. A power distribution or motor control assembly is normally designed to the IEC 61439 series, the electrical equipment of a machine to IEC 60204-1, and the building or plant supply feeding it to BS 7671. The IET says the transition period for BS 7671:2018+A2:2022 ended on 15 October 2026, so new work should reference BS 7671:2018+A4:2026. Everything below is general engineering guidance, not a substitute for the standards or a conformity assessor.

Which standards apply to a UK control panel?

Three documents cover most panels, and they answer different questions. IEC 61439-1:2020 sets out definitions, service conditions, construction and verification requirements for low-voltage switchgear and controlgear assemblies; for assemblies not covered by Part 3 onwards, Part 2 applies, according to the IEC webstore. IEC 60204-1 applies to electrical, electronic and programmable electronic equipment on machines that are not portable by hand while working, and the equipment it covers starts at the point where the supply connects to the machine's electrical equipment. The same IEC page lists its 2016 changes: requirements for power drive systems, revised EMC and protective bonding, clearer overcurrent protection, short-circuit current rating, and a reorganised clause on safe torque off, emergency stop and control circuit protection.

StandardWhat it coversTypical useCheck
IEC 61439 seriesDesign verification and construction of low-voltage switchgear and controlgear assembliesPower distribution, motor control centres, main panelsPart 1:2020 is the third edition; Part 2 is the default for power assemblies
IEC 60204-1Electrical equipment of machines, from the supply connection onwardsControl panels built into machines and production linesIEC 60204-1:2016+AMD1:2021 is the current IEC text; confirm the edition adopted by BSI and in force
BS 7671 (IET Wiring Regulations)Electrical installationsThe supply, cabling and protection feeding the panel18th Edition, Amendment 4:2026 per the IET
IEC 60529 (IP code)Degrees of protection provided by enclosuresChoosing IP rating for dust, water and finger accessListed in HSE's electrical standards table
ISO 13849-1 / IEC 62061Safety-related control functionsPanels containing safety relays or safety PLCsSee our functional safety guide

HSE's own standards table carries a warning worth repeating: "you should ensure that the standard you use is the current one", and the table itself lists older editions, so always check the publisher.

What does UK law require of a control panel?

The law sets duties, and standards are the usual way of showing you have met them. Regulation 4 of the Electricity at Work Regulations 1989 requires that all systems are constructed to prevent danger so far as is reasonably practicable and maintained to the same end, and regulation 12 requires suitable means of cutting off the supply and securely isolating equipment. For product supply, GOV.UK's UKCA guidance lists the Supply of Machinery (Safety) Regulations 2008, the Electrical Equipment (Safety) Regulations 2016 and the Electromagnetic Compatibility Regulations 2016 among the legislation under which a manufacturer can self-declare conformity (with conditions for some machinery), and says Great Britain continues to recognise CE marking alongside or in place of UKCA where product regulations meet UK needs, under the Product Safety and Metrology (Amendment) Regulations 2024. A panel built into a machine is part of that machine's conformity assessment. Which route applies to your product is a question for the manufacturer or a competent assessor; do not guess.

Open industrial PLC cabinet with HMI, PLC racks, terminal rails and a door-mounted fan filter
Open industrial PLC cabinet with HMI, PLC racks, terminal rails and a door-mounted fan filterPhoto: DWI, CC BY-SA 3.0, via Wikimedia Commons

How should you lay out a control panel?

Lay it out so that power, control and field wiring stay physically separated and every component can be reached and replaced. A workable arrangement groups the panel into zones:

  • Incoming supply and isolation: main isolator at an accessible height, branch protection and the 24 V DC power supplies.
  • Control zone: PLC CPU, I/O, safety relays or safety PLC, communication modules and network switches.
  • Power and drive zone: variable speed drives, soft starters and motor protection, placed where their heat and switching noise do not disturb the PLC.
  • Terminal zone: marshalling terminals for field cables, labelled to match the schematic.

Keep power and signal cables in separate trunking runs, cross them at right angles, and put heat-producing devices at the top or in their own airflow path. Leave spare DIN-rail and trunking capacity: adding a module later is far cheaper than rebuilding a full panel.

How do you manage heat inside an enclosure?

Add up the power dissipated by every component, compare it with what the enclosure can reject at the worst ambient temperature, and choose cooling only if the numbers require it. Manufacturers publish power loss in datasheets, drives being the largest contributor. Natural convection works for lightly loaded panels; filtered fans suit moderate heat in clean areas; sealed enclosures with heat exchangers or air conditioners suit dusty, wet or washdown sites. Allow the clearances in each device's installation instructions, de-rate where the datasheet requires, and remember that a fan filter is a maintenance item that needs a place on the planned maintenance schedule.

What wiring and labelling practice do auditors expect?

They expect consistent, traceable wiring that matches the documents. Machine control wiring colours are set by the machine standard and the customer's specification, not by the fixed-wiring colours of BS 7671, so check IEC 60204-1 and the contract before ordering cable. Good practice that survives any specification:

  1. Use ferrules on stranded conductors and terminate to the terminal manufacturer's torque.
  2. Number every wire at both ends to match the schematic, and print the labels rather than hand-writing them.
  3. Keep field wiring on dedicated terminals so a maintenance technician can disconnect a machine without opening the control zone.
  4. Dress cable shields as the instrument or drive manufacturer specifies.
  5. Keep the documentation current: IEC 60204-1:2016 revised its technical documentation requirements, so provide schematics, a parts list, and the supply and short-circuit rating information the standard asks for.

What tests come before you energise a panel?

Work through visual inspection, continuity and protective bonding checks, insulation resistance, and only then controlled power-up and function tests, using the values and methods in the verification clauses of the standard you are building to. HSE explains why care matters: a voltage as low as 50 volts applied between two parts of the body can cause current to flow that blocks signals between brain and muscles, and can stop the heart beating properly. Use test equipment suitable for the purpose; HSE's guidance on electrical test equipment is known as GS38. Record the results, because they are part of the evidence that the panel was built safely.

5 Pro Tips for Control Panel Building

How do you document and hand over a panel?

A panel is not finished until the paperwork matches the metal. Hand over, as a minimum, the final schematics with revision control, the parts list with manufacturer references, the I/O list and network addresses, the PLC and drive backups with software versions, the test records, and the enclosure rating and short-circuit information the machine standard asks for. Photograph the finished layout before the doors close. The next engineer, perhaps you in three years, will fault-find from these records at three in the morning, so a missing page costs real downtime.

Handover itemWhy it matters
As-built schematics and wire numbersFault-finding and safe modification
Component list with datasheetsSpares and obsolescence planning
I/O list, IP addresses, device namesCommissioning, replacement of failed modules
Program and drive parameter backupsRecovery after hardware failure
Test and verification recordsEvidence for the customer and for any later audit
Operating and isolation instructionsSafe maintenance, as required by the duties above

How EDWartens can help

EDWartens UK does not teach panel building or sell panels. Its Professional Module is a five-day live online class in Siemens TIA Portal (PLC, HMI, WinCC SCADA) plus self-paced Basic Engineering, whose video modules include electrical engineering and safety and standards; it costs £2,140 + VAT (£2,568), cohorts start every Monday with a maximum of 10 learners, and it comes with a CPD certificate recording 80 hours of learning. It is not a regulated qualification. If you only want electrical basics first, the free electrical fundamentals course and the electrical wiring simulator cost nothing. You can sign up here.

For the skills that sit around the panel, see our guides to PLC troubleshooting and variable frequency drives.

Start free

Learn electrical and control panels free, then practise the job

Free job simulation

Control Panel Design Engineer

GA drawing, schematics, BOM, heat calculation and the routine test.

The first five days are free, no card needed.

Live UK jobs

Electrical design jobs in the UK

Updated daily, with licensed visa sponsors marked.

Browse all engineering jobs

Frequently asked questions

Which standard should a UK control panel follow?

It depends on the panel's role. Power distribution and motor control assemblies are normally verified to the IEC 61439 series; control panels that form part of a machine follow IEC 60204-1; the supply that feeds the panel is an installation under BS 7671. Many machine panels draw on more than one, so confirm with the product's conformity assessor.

Is BS 7671 the standard for building a machine control panel?

No. BS 7671 is the UK standard for electrical installations such as the supply and fixed wiring feeding a panel. The wiring inside a machine's control panel is governed by the machine standard, IEC 60204-1, whose scope starts at the point where the supply connects to the machine's electrical equipment.

Do I need UKCA marking on a control panel in 2026?

It depends on the product regulations that apply. GOV.UK lists the machinery, electrical equipment and EMC regulations among those where a manufacturer can self-declare conformity, and says Great Britain continues to recognise CE marking alongside or in place of UKCA for many products. Check the specific regulation or ask a competent assessor.

What are the most common causes of heat problems in a control panel?

Under-estimated power loss is the usual cause, especially from drives and power supplies, combined with blocked airflow, clogged fan filters and high ambient temperature. Sum the datasheet power loss of every component, check it against the enclosure's heat rejection at worst-case ambient, and add cooling only where the numbers require it.

Does EDWartens teach control panel building?

No. The Professional Module teaches Siemens TIA Portal PLC, HMI and WinCC SCADA programming online, with self-paced Basic Engineering modules covering electrical engineering and safety and standards. For practical wiring skills you would need a hands-on electrical or panel-building course from another provider.

Sources

  1. IEC 61439-1:2020 — Low-voltage switchgear and controlgear assemblies, Part 1 (IEC Webstore)
  2. IEC 60204-1:2016+AMD1:2021 — Safety of machinery, electrical equipment of machines (IEC Webstore)
  3. BS 7671 — The IET Wiring Regulations (IET Electrical)
  4. Electrical standards and approved codes of practice (HSE)
  5. Electrical injuries (HSE)
  6. Safety in electrical testing at work, INDG354 (HSE)
  7. The Electricity at Work Regulations 1989, regulation 4 (legislation.gov.uk)
  8. The Electricity at Work Regulations 1989, regulation 12 (legislation.gov.uk)
  9. Using the UKCA marking (GOV.UK)
  10. The Supply of Machinery (Safety) Regulations 2008 (legislation.gov.uk)

Share this article

About the author

EDWartens Team

EDWartens Instructional Team

The EDWartens instructional team brings together UK-based automation engineers, certified Siemens and Rockwell specialists, and industry practitioners with decades of combined experience in PLC programming, SCADA engineering, and industrial AI.

View all articles by EDWartens

Ready to become job-ready?

Start with a free course today, or train live in Siemens PLC, HMI and SCADA on the Professional Module.

Related articles